Pre-Installation
Before you begin installation, remember to P.A.C.E. yourself with the checklist below.
P.A.C.E. Pre-Installation Checklist
- Prepare Job Site
- Acclimation
- Control Subfloor Moisture
- Environmental Conditions
Material Preparation
Add 5% extra material for cutting waste and grading allowance. Inspect all planks in daylight for visible faults before installation. Do not install if more than 5% of material is unusable. Install from multiple cartons for best color variation.
Subfloor Requirements
- Must be clean, dry, flat to 3/16" per 10-foot radius
- Wood subfloors: Securely fastened, moisture ≤ 13%
- Concrete: Fully cured (60+ days), moisture barrier required. Max 8 lbs calcium chloride or 90% RH
- Existing hard floors: Must be well-bonded, clean, and level. Fill grout lines
Radiant Heat
Compatible with radiant heat using floating method only. Max surface temp 85°F. Turn system on 3 days before, lower to 65°F 24 hours before installation.
Expansion Gap
Leave 1/4" expansion gap around all walls and fixed objects. Never nail or screw through floated floor.
Floating Click-Lock Installation
Installation Steps
Step 1: Measure room width. Ensure last row is at least 1/3 plank width — adjust first row if needed.
Step 2: Begin along the longest, straightest wall with 1/4" spacers. Cut tongue off first row.
Step 3: Connect planks end-to-end by angling at 20° and pressing down to click-lock.
Step 4: Cut the last plank in each row. Use the remaining piece to start the next row if ≥ 8" long. Stagger joints by at least 6".
Step 5: Angle new rows into the previous row at 20° and press down to lock.
Step 6: Use rubber mallet and tapping block to ensure full engagement. Never strike planks directly.
Step 7: Rip the final row to width maintaining 1/4" gap. Use a pull bar for tight spaces.
Step 8: Remove spacers. Install transition moldings and baseboards.
Glue-Down Installation
Installation Steps
Step 1: Use Titebond 675 exclusively. Dry-fit first two rows and establish a chalk line.
Step 2: Apply adhesive with recommended trowel. Allow proper tack time.
Step 3: Press planks firmly into adhesive. Stagger joints by at least 6". Maintain 1/4" expansion gap.
Step 4: Roll with 100-lb roller. Clean adhesive from surface immediately.
Step 5: Allow 24 hours before foot traffic.
Care & Maintenance
- Sweep or vacuum regularly with a soft-bristle broom or vacuum without a beater bar.
- Damp mop with pH-neutral vinyl cleaner. No steam mops or abrasive cleaners.
- Wipe up spills promptly. Use felt pads under furniture.
- Place doormats at entrances. Maintain temperature 60°F–80°F, humidity 35%–55%.
- Avoid prolonged direct sunlight — use blinds or curtains.
Need Professional Installation?
Our expert installers serve all of Central Florida with up to 5 years warranty coverage.